The Nigerian National Petroleum Company Limited (NNPC Ltd) has achieved a major milestone in the construction of the Ajaokuta-Kaduna-Kano (AKK) Gas Pipeline project, successfully completing the pipeline’s crossing of the River Niger — a significant feat that brings the project closer to its scheduled completion in Q4 2025.
The update was delivered by NNPC Ltd’s Group Chief Executive Officer, Engr. Bashir Bayo Ojulari, during his keynote address at the 24th NOG Energy Week Conference, which opened in Abuja on Tuesday.
Ojulari attributed the progress to effective contract reengineering and collaborative efforts across the energy industry, which have accelerated the pace of delivery for one of Nigeria’s most strategic infrastructure projects aimed at enhancing gas supply and industrial development in the northern corridor.
In another major development, the GCEO announced that Nigeria’s crude oil pipeline network recorded 100% operational availability throughout June 2025, a performance attributed to heightened security interventions led by NNPC Ltd.
“This improved security and availability have directly contributed to a boost in crude oil production,” Ojulari said, while noting that consistent fulfillment of cash-call obligations to Joint Venture (JV) partners has also played a key role in stabilizing operations and investor confidence.
He emphasized that the Petroleum Industry Act (PIA) has positioned NNPC Ltd to better lead the oil and gas sector in financing and executing critical projects.
Looking ahead, the NNPC boss called for increased investments to further drive production and industry growth. He also challenged stakeholders to transform the NOG Energy Week from a “talk shop” into a dynamic platform where performance is celebrated and investment deals are sealed.